The Quiet Phase of ERP Implementations: Testing

Published On: October 22, 2026By

Every ERP project has a stretch where the energy drops. Design is done, the build is mostly done, and go-live is still far enough away that it doesn’t feel urgent yet. That stretch is testing.

No one is presenting to the board. The sponsor has moved on to other fires, and the workshops have ended. What’s left is the client team, a test script and a sign-off box.

That’s where projects are quietly won or lost.

Blank sign-offs are a signal

Remember the operations director from Part 1? The detail that should have worried everyone wasn’t the missed workshops. It was this: test sign-offs came back blank.

A blank sign-off isn’t neutral. It usually means one of three things:

  • The tester doesn’t understand the process well enough to judge it.
  • The tester doesn’t believe the new system will ever replace “how we really work.”
  • The tester has decided that raising issues isn’t worth the trouble.

Meanwhile, the planners were still running production from spreadsheets. The team had quietly built a parallel world, and testing was the one phase that could have exposed it.

When the team goes quiet, you’ve lost your early warning system

During a presentation at a recent event, I spent the most time on one row of the “recoverable or failing” comparison: the team. In a recoverable project, people still say what they see. In a slow-motion failure, they’ve stopped raising issues and stopped attending meetings.

That’s true for our consultants, and it’s just as true for the client’s testers. Testing depends on people telling you what’s wrong. If they’ve gone quiet, the problems haven’t gone away. You’ll simply find out about them at go-live, which is the most expensive time to learn anything.

Discovery debts come due in testing

Another composite from the presentation: a CFO had promised the board a January 1 go-live before discovery was finished. Discovery then turned up three integrations nobody had planned for, plus a data cleanup no one had staffed. Several requirements turned out to be showstoppers that no one had seen coming.

None of that stays hidden. It surfaces in testing, usually as a defect list that no one wants to own. That’s when you hear the most dangerous sentences in a project: “We’ll try.” “We’ll see.” “We should be fine.”

A soft yes today is a broken promise in month nine.

Accountability when no one is watching

If leadership isn’t around during testing, accountability has to be built into how the work runs. These are the practices we lean on:

  1. Say the hard thing early. Bad news is cheapest on the day you learn it. A failed test script reported today is a fix; the same failure found at cutover is a crisis.
  2. Make the risk visible, with an owner. Unsigned scripts, parallel spreadsheets and uncleansed data each belong on the steering agenda as a risk with a named owner. That’s accountability, not blame.
  3. Record who decided. A decision with no owner gets reopened. A RACI and a same-day note in one source of truth, like Azure DevOps, keep testing decisions from being re-argued every week.
  4. Make the client choose. When testing shows the date and the scope can’t both hold, bring priced options, not promises and not refusals. The client owns that decision.

Motivating testers: make it their system

Most client testers aren’t unwilling. They’re overloaded, and they’re being asked to validate something they don’t feel they own.

The move from Part 1 applies here too: give them a real decision. A process owner who shaped the design will test it like it’s theirs, because it is. A tester who got handed a script with no context will click through it and sign, or leave it blank.

And when a tester does raise an issue, treat it like the gift it is. How you respond to the first problem someone reports decides whether they report the second one.

The takeaway

Testing is the phase with the least oversight and the most at stake. The partner’s job is to keep people talking when no one is watching. That means making it safe to report problems and quick to get decisions. Everything goes on paper.

Your turn: When did a soft yes during testing come back to cost you?